This newsletter provides key updates on the Mead Way scheme and details of any road closures and diversions which may affect you, your staff or your customers.
Work on phase two from Westmead roundabout to Withymead roundabout is continuing:
Work to replace the safety barrier on the bridge, and waterproofing under the new lane has started.
The utility companies have begun their careful work to move the utilities under the new northbound lane. This needs to be done in a sequenced approach as a number of pipes and cables are currently stacked on top of each other.
The contractor is continuing to build the new northbound lane from Westmead roundabout to the Withymead roundabout with new kerbs starting to be laid.
The extensive drainage work to connect phase two to phase one (from Meads roundabout to Westmead roundabout) and the stream running through the subway is continuing, with the footpath that was previously removed, beginning to be reinstated.
If you would like to receive regular updates on all highways schemes across the Borough, why not sign up to receive the three-weekly Highways News newsletter. The next edition is out later this week.
Please forward this newsletter on to anyone you think would find it useful. They can sign up to the newsletter using this link