More than 200 days have been lost on the scheme due to a combination of utility companies or their sub-contractors not being able to attend the site during the first national lockdown while, in recent months, the scheme has suffered as utility contractors have been unable to attend the site due to a backlog of work caused by the pandemic.
Further delays were caused by wildlife issues within Phase 2. Mitigations were in place against these risks but the scheme was still adversely affected.
High level discussions have taken place between ourselves and a number of utility companies in order facilitate the works within a reasonable timeframe.
No extra borrowing is required for the works at Mead Way, as the funding is covered by Section 106 of the Town and Country Planning Act 1990.
|