Four Lakes Community -
We are seeing the most rain and flooding in Gladwin and Midland counties since 2020. FLTF is monitoring flows and lake levels and communicating with county emergency managers per protocol. Lake and river levels are elevated throughout Michigan. Water is flowing through all four dams as expected and we see no integrity issues with the dams at this time.
We are receiving inquiries asking why we aren’t doing more to control flooding downstream. As a reminder, the dams are not intended for flood control, nor do the lakes have the capacity for flood control storage. The dams are designed and operated as run-of-river, with the intention of not increasing downstream risk from dam failure.
The weather over the last several weeks has slowed construction as crews have not been able to perform work with high levels of water passing through the spillways. While we want to regain construction momentum, the water must recede first.
The Sanford Lake Dam is now operational. What follows in this news flash are guidelines for using and experiencing Sanford Lake. This is an exciting milestone, but full success will be achieved when all four dams and their lakes are safely restored!
Sincerely,
Dave Kepler,
President and Chair, Four Lakes Task Force
|