If you missed the October 9 informational webinar, you can watch the recording and view the presentation slides here.
Key takeaways from the webinar:
- Work will suspend on Secord and Smallwood by the end of October, and work will suspend on Sanford by the end of February
- At suspension, each dam will exceed the safety of the dams as they were in 2020, and meet at least a 200-year flood event
- However, the dams will not meet their intended safety standards as-permitted until they are complete
- FLTF will have approximately $10 million of the State of Michigan grant remaining once all dams are suspended by March 2025
- We hope for an oral hearing to be scheduled with the Michigan Appellate Court in December
- Dams cannot be left in suspended conditions, as they are in transitional states
|